The one-time downstairs patio tiling will start at Buildings 8, 9 and 7 in that order. If there is tile on your patio, the demo and replacement should take about a week and a half. A bare patio will take about a week. Plain patio paint will take a few hours. 
 
Prepping the patios on building eight will start this week. There will be some noisy grinding to level the patio surface. Actual tile application and grouting will start in late August. Sorry, we can’t give you exact dates. The construction world doesn’t work that way.
 
Tile saws are incredibly noisy.
 
Please notify your property managers.